Power lines and transformers on a utility pole, the equipment behind a new electric service connection
Home / Blog / Incentives & Policy
INCENTIVES & POLICY

California Moves to Enforce Utility Energization Timelines for SCE and SDG&E. What Commercial EV Charging and Electrification Projects Should Know Before a Vote as Early as December 17

California utility energization timelines could soon get an enforcement step. On November 16, 2026, the California Public Utilities Commission mailed a proposed decision that would require PG&E, SCE and SDG&E to file a remedial action plan whenever they miss the state's targets for connecting new and upgraded electric service, and to jointly hire an independent auditor under Senate Bill 254 (2025). The earliest the Commission can vote is its December 17, 2026 business meeting.

Status: proposed, not adopted. For a developer, property owner or fleet manager in Orange County or anywhere in Southern California, the bigger point is that the targets themselves are already in effect. If your EV charging project or building electrification job is waiting on SCE or SDG&E, you should know what those targets are, how to document your own steps, and how to report a delay.

What the CPUC proposal would do

The proposed decision (Agenda ID 24654, Rulemaking 24-01-018) builds on Decision 24-09-020, which the CPUC adopted on September 12, 2024 and issued September 17, 2024, to set energization timelines for the three large utilities. According to the proposed decision, it would:

The proposed decision does not change the timelines, set new penalty amounts or create a payment to customers. Enforcement would run through the CPUC's existing enforcement policy (Resolution M-4846), and Energy Division could issue warning letters or notices of violation or refer matters to the CPUC's enforcement division. Projects that need upstream capacity work, such as a new circuit or substation, are left for a possible future decision. Auditor costs would default to ratepayers: the utilities would track them in memorandum accounts and could later request recovery in a rate case.

California utility energization timelines already in place

The utilities publish the targets from D.24-09-020 for their customers. According to SCE's energization overview and SDG&E's Energization Timelines Guide, for projects that do not need upstream capacity upgrades:

SDG&E's guide notes that no more than 5% of projects may exceed the maximums, and it describes Rule 45 as EV charging infrastructure for commercial and multifamily properties. Two limits matter. First, SCE says the targets apply only to the parts of the process fully under its control, so time spent on your permits, easements, payments and site work does not count against the utility. Second, projects that need a new circuit or substation have far longer maximums in SDG&E's guide.

Why accountability is the issue now

The utilities report progress twice a year, but SDG&E's September 2026 report and SCE's September 2025 report did not yet show what share of projects meet the targets. In its September 30, 2026 biannual energization report, SDG&E said it remains unable to fully populate the reporting requirements and listed customer funding, material procurement, land rights, Caltrans and FAA reviews, and municipal moratoriums as constraints. The proposed decision ties remedial plans and audits to those same reports, which is why it matters for anyone with a project in the queue.

It also pairs with another item on the CPUC calendar. Our November 9 post covers a separate proposal, up for a vote as early as December 3, that would let some commercial EV chargers and batteries connect before grid upgrades finish.

What this means for your project

The targets give you a benchmark for planning and a basis for asking questions. Practical steps for a commercial EV charging, battery or electrification project:

  • Apply early and completely. Under SCE's process, the clock starts once SCE notifies you that your application is complete. Incomplete applications can delay that date.
  • Know your tariff path. Ask the utility whether your job is a Rule 15, Rule 16, Rule 29 or Rule 45 project, or a combination, since the maximum timeline depends on it.
  • Ask about capacity first. If the circuit or substation needs an upgrade, the standard targets do not apply; much longer maximums do, according to SDG&E's guide. Ask about capacity during design, before you order equipment.
  • Finish your steps fast. Permits, easements, fees and site construction work such as trenching are customer steps in both SCE's and SDG&E's guides. Track the dates you complete each one.
  • Keep a dated record. Log every submission, utility request and response. If a project stalls, that record is what a utility project manager or the CPUC will ask for.
  • Report delays. SDG&E's fact sheet says customers can report energization delays to the CPUC through its customer delay reporting form.

How Burge Energy can help

Burge Energy designs and builds commercial solar, battery storage and EV charging systems for new and existing buildings across Orange County and Southern California. We can prepare complete load and design packages for your utility application, coordinate permits and site work so your side of the clock moves quickly, screen incentive programs, and track the project with SCE or SDG&E through energization. Burge has been building in Southern California since 1977, and we are licensed (CSLB) and covered for solar, storage and EV charging work. Learn more about Burge Energy, review current incentives, or Request an Energy Assessment.

Sources

Incentive eligibility depends on project specifics. Confirm with your tax advisor and the program administrator before relying on any figure here. Utility timelines also depend on site conditions and grid capacity, so confirm them with your utility. This article is general information, not legal, tax or financial advice, and it is current as of November 23, 2026. The proposed decision may be revised or held before a vote.

← All articles

Planning solar, storage or EV charging?