Electric cars charging under a solar panel canopy in a commercial parking lot
Home / Blog / Incentives & Policy
INCENTIVES & POLICY

California's Fast-Track EV Charger Permit Law Expands to Canopies and Batteries on January 1. What Southern California Site Owners Should Do Now

California EV charger permitting gets broader on January 1, 2027. Senate Bill 1283, chaptered on September 20, 2026 as Chapter 347, Statutes of 2026, requires cities and counties to administratively approve EV charging stations that include a canopy or onsite energy storage sized to support charging. Those canopy and storage approval rules take effect January 1, 2027, and the bill's changes to the permit timeline section of the Government Code are expressly operative that day.

Status: enacted. For a commercial owner, developer or fleet manager in Orange County or anywhere in Southern California, that means a solar carport over chargers, or a battery that keeps a charging site within its utility service limits, is part of the station that SB 1283 requires the city or county to approve administratively, rather than a separate discretionary project. Here is what changed, what did not, and how to plan a 2027 project around it.

What SB 1283 changes for California EV charger permitting

Streamlined charger permits are not new. Under existing law described in the Senate Judiciary Committee analysis, cities and counties must approve charging stations through a building permit or similar nondiscretionary permit, limit review to health and safety, and adopt an expedited permitting ordinance and checklist. The analysis also notes that the author saw ambiguity in that law keeping localities from streamlining add-ons such as canopies and onsite storage, which some treated as separate or discretionary projects.

The chaptered bill closes that gap:

  • Canopies and storage included. Stations with a canopy or onsite energy storage sized to support charging must be approved administratively.
  • Supporting work included. Local streamlining ordinances must cover infrastructure needed for or accessory to a station, such as paving, concrete pads, utility trenches, canopies and energy storage.
  • Canopy size limits. The law defines a canopy as an overhead structure with clearance of 17 feet or less, fascia width of 4 feet or less, and coverage of 5,000 square feet or less. A larger structure may not qualify.
  • Written notice of approval. When an application is deemed approved, the local agency must send written notice within 30 days listing the permits granted, and the applicant may begin construction before that notice arrives.
  • A fallback application. Where a city has not updated its ordinance or checklist, the bill lists the project details an applicant must submit, such as location, equipment ratings, site grade, and canopy and storage data. GO-Biz must adopt a standardized application form and post an optional compliance template; the law sets no deadline, and neither had been posted on the GO-Biz readiness page as of November 16, 2026.

Cities and counties have until December 31, 2027 to amend their ordinances and checklists. Local review is not eliminated: agencies can still require plans and documentation to verify health and safety compliance, and they still inspect the finished station.

The permit clock that already applies

SB 1283 builds on deadlines enacted in 2021 by AB 970 and in effect since January 1, 2022. According to the Senate Judiciary analysis, an application is deemed complete if the building official identifies no deficiencies within 5 business days for 1 to 25 chargers at a site, or 10 business days for more than 25. It is deemed approved if the official has not acted within 20 business days after completion for up to 25 chargers, or 40 business days for more than 25. The chaptered text restates those deadlines and does not appear to change them.

The California Attorney General's March 18, 2025 legal alert to local planning directors adds points owners often miss. Localities cannot limit charging stations to commercial areas or otherwise restrict them by zoning. According to the AG alert, the rules cover personal, public and fleet charging for light-, medium- and heavy-duty vehicles, whether charging is an accessory or the primary use of a site. The same alert notes that other state laws still apply, including the Coastal Act for development in the coastal zone, which matters for sites in coastal Orange County cities.

Local readiness varies. The GO-Biz Plug-in Readiness page currently lists 373 cities and counties as streamlined, 76 with streamlining in progress and 91 not streamlined. Those counts track compliance with the existing streamlining law, not SB 1283's new canopy and storage provisions, which cities have until December 31, 2027 to adopt.

Two companion laws to know

SB 1283 was signed with a package of charging bills. Two others affect commercial and multifamily sites.

SB 969: charger inspections. Chaptered as Chapter 346, Statutes of 2026, it covers EV charging equipment used for commercial purposes under California's weights and measures system. Equipment that is factory tested and certified for metrological requirements by a factory registered service agency is exempt from field placement and field tolerance testing. Operators must file a placed-in-service report with the county sealer within 72 hours of installation. The California Department of Food and Agriculture must update its charging equipment regulations by July 1, 2028.

AB 1820: permit fees at apartment buildings. Chaptered as Chapter 348, Statutes of 2026, it limits what a city or county can charge to permit Level 2 chargers at new or existing multifamily developments. The fee cap is $500, plus $5 per kW from 51 kW to 250 kW, plus $2 per kW above 250 kW, unless the agency adopts a resolution or ordinance with written findings showing a higher reasonable cost. The cap is repealed January 1, 2036. It is operative July 1, 2027 for most jurisdictions, and January 1, 2028 for cities and counties under 200,000 residents.

What this means for your project

The law makes the permit path clearer. It does not change utility service timelines, fire code requirements or equipment listings. Practical steps for a 2027 project:

  • Design the canopy to the definition. If a solar carport is part of the plan, check clearance, fascia and coverage against the SB 1283 canopy limits early. If a structure exceeds these limits, ask the building department how it will be reviewed.
  • Size the battery to the charging load. The streamlined path covers storage sized to support charging. Document how the battery supports the chargers, for example by managing peak demand within the site's electrical service.
  • Ask your city for its current checklist. Find out whether it already covers canopies and storage, or whether you will submit under the fallback application list after January 1.
  • Track the clock. Record the date your application is submitted and the date it is deemed complete. Under Gov. Code 65850.71, the 20 or 40 business day approval window runs from the date the application is deemed complete.
  • Check for the coastal zone. For coastal sites, confirm early whether a coastal development permit is needed in addition to the building permit.
  • Plan inspections and registration. For chargers that sell electricity to drivers (commercial purposes under SB 969), ask your equipment supplier whether the chargers were factory tested and certified by a factory registered service agency, and assign who files the county sealer report.
  • Start the utility application in parallel. The permit is often not the longest step. Request your utility's capacity review while design is underway.

How Burge Energy can help

Burge Energy designs and builds commercial solar, battery storage and EV charging systems for new and existing buildings across Orange County and Southern California. We can lay out chargers, solar canopies and storage as one project, prepare permit drawings and checklists for your city, screen incentive programs, and coordinate with your utility through energization. Burge has been building in Southern California since 1977, and we are licensed (CSLB) and covered for solar, storage and EV charging work. Learn more about Burge Energy, review current incentives, or Request an Energy Assessment.

Sources

Incentive eligibility depends on project specifics. Confirm with your tax advisor and the program administrator before relying on any figure here. Permit requirements also vary by city, county and site, so confirm them with your local building department. This article is general information, not legal, tax or financial advice, and it is current as of November 16, 2026.

← All articles