On October 23, 2026, the California Energy Commission (CEC) released a California battery storage grant solicitation worth up to $46,144,000 (less any amounts set aside for state cost sharing on water utility projects) for new distributed energy resources that add supply or reduce or shift demand when the grid is stressed. It is the Distributed Electricity Backup Assets (DEBA) program's solicitation GFO-26-503, and applications are due January 26, 2027, per the CEC solicitation page. The pre-application workshop is this Thursday, November 5. If you run facilities for a city, special district, water agency, tribe or nonprofit in Southern California, this solicitation is worth reviewing now: the application packet includes budget, schedule and commitment letter forms, per the solicitation page, and the June draft required site control and committed match.
What the CEC opened, and its status
Status: open solicitation. The solicitation is authorized under SB 105 (Chapter 104, Statutes of 2025) and AB 113 (Chapter 248, Statutes of 2026), per the CEC solicitation page. The DEBA program page says SB 105 appropriated $46,144,000 of Proposition 4, the 2024 climate bond, to DEBA. The CEC says the goal is to deploy new resources that help avoid blackouts during extreme events, per the solicitation page.
Key dates from the CEC solicitation page:
- November 5, 2026, 1:00 to 4:00 p.m.: pre-application workshop (remote only)
- November 13, 2026, 5:00 p.m.: deadline for written questions
- January 26, 2027, 11:59 p.m.: applications due through the CEC's ECAMS online portal
The money also has to move quickly. The CEC lists a June 30, 2028 encumbrance deadline and a June 30, 2030 liquidation deadline for these Prop 4 funds in its February 2026 program slides and on its earlier Prop 4 DEBA announcement page, which also says projects must come online quickly and show capacity that is incremental to the state's existing Resource Adequacy supplies and Strategic Reliability Reserve.
Who can apply, and where private owners fit
This is not a grant a private company can apply for on its own. CEC staff slides from February 2026 list the eligible applicants as public agencies, local agencies, nonprofit organizations, special districts, joint powers authorities, public utilities (including investor-owned utilities), local publicly owned utilities, mutual water companies and tribes. The June 2026 draft solicitation workshop slides repeat that list and do not include private commercial companies.
Private sites may still have a role. The June draft allowed both behind-the-meter and front-of-the-meter projects at non-residential and aggregated residential sites. It accepted site control in the form of an executed lease, host site agreement, recorded easement or proof of property, and required a letter of commitment when a project partner provides the site, per the draft solicitation and draft workshop slides. That suggests a privately owned commercial site could host a project led by an eligible applicant, such as a utility, nonprofit or joint powers authority, but the draft does not say so directly. Confirm with CEC staff before building a plan around it.
What projects qualify, per the draft
The final solicitation manual governs. The points below come from the June 23, 2026 draft workshop slides, so check each one against the final manual on the CEC solicitation page.
- Eligible technology: new, zero-emission equipment, including battery energy storage, thermal storage, load flexibility controls (smart HVAC controls, water heater controllers, variable frequency drives), bidirectional vehicle-grid integration infrastructure, waste heat-to-power and microgrid controllers.
- Not eligible: solar PV, wind, diesel generators and other non-zero-emission generation, and load-only appliances such as EVs themselves.
- Award size: per the draft slides, a proposed minimum of $2,000,000 and maximum of $8,000,000 per award.
- Match: per the draft slides, a proposed minimum match of 25% of the CEC request, in cash or in kind, with commitment letters due at application.
- Performance: per the draft slides, projects pick one of four dispatch pathways and perform for three program seasons, with a May 1 to October 31 season and nominated capacity available from 4:00 to 9:00 p.m. daily.
Two takeaways for Southern California owners. First, solar PV is not an eligible technology under the draft; storage, load flexibility controls and microgrid controllers are. Second, the dispatch obligation is real. A battery funded through this program has to be available on the CEC's schedule for multiple summers, which affects how much of it you can also use for your own bill savings or backup power.
What this means for your project
If your organization is an eligible applicant, or you own a site that could host one, the weeks before the January 26, 2027 deadline matter. These steps are practical preparation, not a judgment about whether your project will score well.
- Attend the November 5 workshop. Listen for any changes from the June draft on award size, match and dispatch pathways.
- Submit questions by November 13. Ask about private host sites, how behind-the-meter capacity is measured and whether existing systems can be expanded.
- Lock in site control. Line up a lease, host site agreement or letter of commitment early. Each site needs one.
- Build the match. Under the draft's 25% minimum, an $8 million request needs at least $2 million in committed match, per the CEC's own example in the draft workshop slides. Identify the source now.
- Gather technical basics. Collect 12 months of utility bills and interval data, your electrical single-line diagram, available space for equipment and your utility's interconnection requirements.
- Plan for the timeline. The June draft projected proposed awards in spring 2027 and agreement starts in summer or fall 2027, per the draft workshop slides. Equipment lead times and utility review need to fit inside that window.
If your organization is not eligible and has no partner that is, this grant is not your path. Battery storage can still be worth evaluating on bill savings, backup power and federal tax credits, which we covered in our post on the commercial solar tax credit 2027 deadline, and on our Incentives page. Under the June draft, DEBA funds combined with tax credits and other support could not exceed 100% of eligible project cost.
How Burge Energy can help
Burge Energy designs and builds commercial battery storage, solar and EV charging for new buildings and existing sites across Orange County and Southern California. For grant-funded projects, we can help scope the system, prepare the technical inputs an application needs (equipment layout, single-line diagram, schedule and construction budget), screen for other incentives and coordinate with SCE and SDG&E on interconnection. Burge has been building in Southern California since 1977, and we are licensed for solar, storage and EV charging work. Request an Energy Assessment to see whether storage fits your site before the January 26 deadline, or learn more about Burge Energy.
Sources
- GFO-26-503: Distributed Electricity Backup Assets Program, Distributed Energy Resources (DERs) for Grid Reliability, California Energy Commission, October 23, 2026
- Prop 4 Distributed Electricity Backup Assets (DEBA) Grant Program, California Energy Commission (earlier announcement), 2026
- Distributed Electricity Backup Assets Program, California Energy Commission, accessed November 2, 2026
- DEBA Prop 4 Draft Solicitation Workshop Presentation, California Energy Commission staff, Docket 22-RENEW-01, June 23, 2026
- Draft Solicitation, Distributed Electricity Backup Assets Program, DERs for Grid Reliability, California Energy Commission, Docket 22-RENEW-01, June 2026
- Pre-Application Workshop, GFO-26-503, California Energy Commission, November 5, 2026
- DEBA Prop 4 Public Slides, Program Update, California Energy Commission, February 20, 2026
Incentive eligibility depends on project specifics. Confirm with your tax advisor and the program administrator before relying on any figure here. This article is general information, not legal, tax or financial advice. Facts are current as of November 2, 2026; program terms can change.